Department of Agrarian Reform
Republic of the Philippines
.png)
ARBDSP MES & Library
Support Services Office

Tulay ng Pangulo sa kaunlarang pang-agraryo
(TPKP) Project


Project Profile
Project Title: Tulay ng Pangulo para sa Kaunlarang Pang-Agrarayo (TPKP)
Donor : French Assisted
Executing Agency : Department of Agrarian Reform
Implementing Agency (IA) : Department of Public Works and Highways
Unified Project Management Office (UPMO)
Bridges Management Cluster (BMC)
Loan Proceed : PhP 16,511,090,000.00
GOP: PhP 1,963,564,000.00
Total: PhP 18,474,564,000.00
Loan Signing: December 24, 2008
Project COST
Implementing Schedule:
Original Project Duration (5years) : March 2009 - December 2013
Extension thru DAR-DPWH-Matiere MOA : January 2014 – December 2017
DAR-DPWH Amended MOA : January 2018 – December 2020
Revised Target Completion : December 2022
Original Physical Target : 418 Bridges
Revised Physical Target : 188 Bridges
Parent Locations : Agrarian Reform Communities (ARCs) and/or
Comprehensive Agrarian Reform Program (CARP) Covered Areas
Project Duration
With lack of budget due to the lapsing of appropriations and limited time for project implementation, the DPWH, as the Implementing Agency, deemed it necessary to implement bridge projects that are most critical and necessary as well as those which are immediately implementable, considering proximity to on going DPWH projects and to the depots. As such, as agreed, instead of implementing more than 400 single-lane (SL) bridges to accommodate as many Congressional Districts as possible, the DPWH and DAR agreed to consider Double-lane (DL) bridges, whenever more feasible and necessary. Thus, of the 287 earlier endorsed bridges, only 188 bridges shall be completed. To date, 81 bridge projects are completed and 17 bridges on-going construction works and 90 are under various pre-construction stages (of the 90 pre-con., 15 for implementation this year).
Project status: 2016 - present